2019/06/25 Toyosu campus floor switch replacement work
During the summer period, the floor switch will be replaced at the Toyosu Campus.
We apologize for the inconvenience and inconvenience of users, but we ask for your understanding and cooperation.
1. Construction period:
August 7-30, 2019
2. Construction details:
Replacing network switches installed on each floor
- Removing wiring from the switch
- Switch replacement
- Wiring label replacement
- Connecting wiring to the switch
- Connection check
3.Notes:
During the work period, the network stops in the target area, and devices that use the network such as telephones, surveillance cameras, classroom AV equipment, office terminals, multifunction devices, and wireless LAN cannot be used.
It is expected to stop for several hours at each location.
4. Contact information:
IT system division
(Extension 7530, goiken@sic.shibaura-it.ac.jp)
Date | School building and floor for construction |
---|---|
8/7 (Wednesday) | Interchange Building 1F ・ 4F ・ 5F |
8/8 (Thursday) | Interchange Building 6F, Large Lecture Room, Classroom Building 1F |
8/9 (Friday) | Interchange Building 2F /3F, Classroom Building 2F, Research Building 2F-4F (Classroom side) |
8/10 (Sat /legal inspection) | Research Building 3-5F (Classroom side) ・ 7F |
8/11 (Japanese and legal inspections) | Research Building 1F ・ 2-3F (Laboratory side) |
8/12 (Month and legal inspection) | Research Building 4-5F (Laboratory side) /Research Building 6F |
8/13 (Tue) | Research Building 8-9F |
8/14 (Wednesday) | Research Building 10-11F |
8/15 (Thursday) | Research Building 12-14F |
8/20 (Tue) | Classroom building 3F-5F |
8/22 (Thursday) | Server room (NOC7) /Archiplaza |
8/23 (Friday) | Server room (NOC7) |
8/26 (Mon)-27 (Tue) | Classroom Building 6F PC Lecture Room |
8/28 (Wednesday) | Classroom building 6F PC training room 1-5 |
8/29 (Thursday) | Classroom Building 6F PC Training Room 6 |